Which of the following is one of the phases of rolling in asphalt construction?

Prepare for the QMS Roadway Test. Enhance your readiness with flashcards and multiple choice questions, each question includes hints and detailed explanations. Gear up for success!

The breakdown phase is a critical step during the rolling in asphalt construction. This phase occurs after the hot asphalt mix is placed and is aimed at achieving a reduction in thickness while ensuring proper compaction of the surface layer. During the breakdown phase, the weight and vibration of the rollers compress the asphalt mix to eliminate air voids and ensure proper interlock of the aggregate particles.

The effectiveness of this phase is crucial because it helps to enhance the durability and overall performance of the asphalt surface. Proper execution during the breakdown phase leads to a well-compacted layer that can withstand traffic loads and weather conditions. This phase typically requires careful consideration of roller type, speed, and weight to ensure the asphalt achieves the desired density without damaging the mix.

The other phases, while related to the overall process of paving, do not specifically define the immediate compaction requirement following the placement of the asphalt mix. For example, the base phase generally refers to the preparation and laying of the base material prior to asphalt application, while the surface phase often refers to the final layer that is compacted and finished. The layer phase can refer more generally to the different layers of material involved in the roadway construction, but it does not highlight the specific compaction efforts required after asphalt placement like the

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy